Is there any way to show if a task was overdue?

Last post 07-07-2008 14:10 by Karine. 2 replies.
Page 1 of 1 (3 items)
Sort Posts: Previous Next
  • 06-30-2008 18:41

    Is there any way to show if a task was overdue?

    If a task is due on, say, October 1 but is not completed until October 5, is there any way to reflect this in a report?

     

    Thanks! 

    Filed under:
  • 07-07-2008 13:58 In reply to

    Re: Is there any way to show if a task was overdue?

    Hello Mr. Jackson,

     

    A task that was overdue will not automatically appear highlighted or coloured in a report.

     

    If you wish to generate reports where tasks that were overdue are isolated, one way to do so is to have two different task statuses for completed tasks (for example, «Completed on schedule» and «Completed after due date». You could then set up a custom task report and filter using your «Completed after due date» status. Ideally, this would mean that your projects, from this moment forward, would be based on a project template where these statuses have been created.

     

    If we may be of any further assistance with regards to this matter, please feel free to reach us again.

     

    Thank you for using AceProject.

    Michel Deslandes - Your AceProject Resource
    Customer Service
    Live Chat: http://messenger.providesupport.com/messenger/aceproject.html
    Email: support@aceproject.com
    Phone: 1-866-259-2454 (US & Canada) / +1-418-907-5184 (International)
    Fax: 418-907-8089
    Website: http://www.aceproject.com
  • 07-07-2008 14:10 In reply to

    • Karine
    • Top 10 Contributor
    • Joined on 02-11-2008
    • Quebec City
    • Posts 32

    Re: Is there any way to show if a task was overdue?

     Hello Mickey,

    Your other option would be to run a Task report by date, and show all tasks due before today. This way, you will only see the tasks that were due before today. You then sort your tasks by status and focus on the incomplete tasks.

    You can also compare a task's due date with it's last update. Normally, with your example, you would see the due date as October 1st but the last update as October 5th.

    Karine Simard
    Customer and Marketing Relations
    Websystems, inc
    www.aceproject.com