  • 10-01-2008 16:53

    • ldavis
    • Top 50 Contributor
    • Joined on 10-01-2008
    • Posts 2

    Feature?(bug): Administration - User Workload Daily View

    I was attempting to get a handle on the number of hours assigned to people for a given day.  The User Workload Daily view seemed to be my answer.

    However, while I was using this feature of the site I ran into a problem.  I had two people allocated to a task that starts/ends today for 8 hours.  When I looked at the daily view report view it displayed both users having 8 hours due today.  I was perplexed I was thinking it would be 4 hours not 8.  I thought this may be a feature of the product.  It automatically calculates the 8 hour task estimate to each member of the project.  So I was mistaken and should have only entered 4 hours as the estimate. 

    I changed the stimate looked at the project % complete. It showed 200% completed and 8 hours spent.  Each person had entered 4 hours on their timesheet.  I thought about this some more and realized something just didn't seem right between these two.

    Having a task with multiple people allocated to it seems reasonable, but the problem comes into play when they have disporportionate amounds of work.  say one is doing 75% of the work while the other is doing 25% of the work.  This complicates things further.

    It seems as if should enter in the total hours estimate for everyone and then allocate each person a percentage of the time.  The Daily workload view should use those percentages and the duration of the task in it's calculations.

    The only work-around I can see at this point is to have only one person assigned to a task. This overloads the schedule with redundant tasks.

    Overall the product has been easy to use and straight forward.  No syntax errors have been encountered; but this one logic error has me perplexed!

    Regards...

  • 10-02-2008 9:17 In reply to

    Re: Feature?(bug): Administration - User Workload Daily View

     Hello Mr. Davis,

    In your case, entering 8 hours for the estimated number of hours for that task was the right thing to do. When using AceProject's User Workload feature, you will notice, amidst the filters, there is a «Divide Between Assigned Users» checkbox that you must enable if you want AceProject to divide the task estimated hours evenly among it's assigned users. AceProject will not allow you, however, to specify the percentage of the task workload that will be allocated to each of its assigned users.

    Michel Deslandes - Your AceProject Resource
    Customer Service
    Live Chat: http://messenger.providesupport.com/messenger/aceproject.html
    Email: support@aceproject.com
    Phone: 1-866-259-2454 (US & Canada) / +1-418-907-5184 (International)
    Fax: 418-907-8089
    Website: http://www.aceproject.com
Page 1 of 1 (2 items)
Copyright © 2001-2008 Websystems Inc.