How is the Actual Task Hours field value calculated?

Actual Task Hours represent the total number of hours users entered in their time sheets against specific tasks in the project. Only time items with an “In progress”, “Submitted” or “Approved” status are taken into account. Rejected time isn’t.

Read More

How is project progress calculated?

The % Done you see just below the Status field in the Edit Project Information page is the same as the Estimated Average % Done which may be displayed in the  Home => Projects > Projects page. This is also the value used in the project Gantt charts to display overall progress on the projects. This […]

Read More

How can I assign users to a project?

Here are the steps to assign users to a project: Make sure the users have been created in your AceProject account. Only administrators can create users. Please refer to this knowledge base topic to learn more about user creation. If you already have a project tab in the top frame for that project, click on it and […]

Read More

Who can edit a project’s parameters?

Administrators and project managers can edit a project’s parameters (Number, Name, Dates, Associated Client,  Task Group values,  Task Type values, etc.). As for other Normal users assigned to the project with the “Can Open this Project” access right, they can see the entire project’s structure but in read-only mode.

Read More

How is the Actual Total Hours field value calculated?

Actual Total Hours represent the total number of hours users recorded in their time sheets against the project, whether on specific tasks or without specifying a task. Only time items with an “In progress”, “Submitted” or “Approved” status are taken into account. Rejected time isn’t.

Read More