Why doesn’t the system let me set dates for a task?

If you are not able to set dates for a task, it is either because the task has been set to completed (in which case  a Project Manager or an Administrator would need to reopen the task for further modifications) or because you do not have sufficient Edit Task Level rights on the project. For […]

Read More

How does the Finish-to-Start dependency work?

A “Finish-to-Start” mandatory dependency means that a predecessor task must be set to completed before its successor may be started. If a lag time is also provided on the “Finish-to-Start” mandatory dependency, that time will need to elapse (after the predecessor has been set to completed) before the successor task may be started. In AceProject, […]

Read More

How can I add and assign a task?

Under Home  =>  Tasks -> Tasks, you may click on the “Add a task to this project” button and then select the appropriate project. You may also add a task to a currently open project by clicking on the right edge of the project tab in the top frame and then selecting “Add a task” in the […]

Read More

What’s the Lag Time?

“Lag Time” represents the number of days that must elapse after a predecessor task is completed before its successor may be started. For instance, if  task 1 (the predecessor) is to apply the 1st coat of paint on a wall and task 2 (the successor) is to apply the 2nd coat of paint, a lag […]

Read More

How are Actual Hours calculated?

Actual Hours are calculated based on timesheet entries recorded by users. For information on the different ways for users to record actual hours in AceProject, please refer to the following help topic.

Read More

How to create a task by email?

First, copy the email link for the email address. The email address is unique for each project and can be found under Edit Project by clicking on the email icon at the top right. Second, paste it into the To: section of an email from your email client. The subject becomes the Task Summary, the […]

Read More